New-Built Operations
Support Base - IJmuiden (NL)

Follow our journey towards the future!

November 14, 2024

We are proud to announce that N-Sea Group has signed a contract to build a new operations support base with our valued partner MSCY B.V. who develops and operates facilities at Zeehaven IJmuiden Port (NL).

Dennis Stolk, Director Assets of N-Sea Group states:

“We are excited that N-Sea has been able to secure this prime location for development of its future primary operations support base. As per Q4 2025 we shall able to support all our offshore activities in the Europe region from one unique location. Bringing together maintenance, repair, storage, and logistical activities under one roof on one location allowing N-Sea to provide safer and more efficient operations. Through this initiative N-Sea will be positioned to extend its subsea solution service portfolio and capabilities, in alignment with current and future needs of our valued customers.”

Jasper Joosse, Manager Operations OSB IJmuiden of N-Sea adds:

“The unique location and (organisational) set-up allows us to optimally manage our asset base and support, our growing fleet, and project volume from one location. Standardising work methods, the use of digitised track & trace systems, all supported by a dedicated team of in house technicians and experts will allow us to reduce operational down time within our projects to a minimum. The offshore support base is strategically well-situated with open access to the North Sea, without the need of using the locks of the North Sea Canal. As such the port is within 20 minute drive from Amsterdam and Schiphol Airport.”

The new-build base is planned to be completed and fully operational as per end Q4 2025, the outdoor storage yard will enter into use already from mid Q1 2025 onwards.

Stay tuned

On this page, we will regularly share updates, milestones, and behind-the-scenes photos as construction progresses.

Check out the timeline below and follow our journey!

April 2025

Construction works have commenced, outside area already in use

After completing the foundation works, construction works on the warehouse and offices has started. N-Sea has  already started to use the outside storage area.

March 2025

Foundation completed and steel construction rising

The foundation work is finished and the construction of the steel framework has begun. The outline of our new base is taking shape!

February 2025

Outside area (phase 1) and fencing in place, foundation works started

The first phase of the outside area and fencing is completed and ready for use by N-Sea. Foundation works have started on the new Operations Support Base.